+86-29-81778206 / 81778300       jingying@cctegxian.com
Products & Services Company
You are here: Home / Products & Services / Geological Engineering And Disaster Management / Foundation Pit Engineering / Foundation Treatment Engineering Inspection
Foundation Treatment Engineering Inspection
Foundation Treatment Engineering Inspection Foundation Treatment Engineering Inspection
Foundation Treatment Engineering Inspection Foundation Treatment Engineering Inspection
Foundation Treatment Engineering Inspection Foundation Treatment Engineering Inspection
Foundation Treatment Engineering Inspection Foundation Treatment Engineering Inspection
Foundation Treatment Engineering Inspection Foundation Treatment Engineering Inspection

loading

Foundation Treatment Engineering Inspection

Share to:
facebook sharing button
twitter sharing button
line sharing button
wechat sharing button
linkedin sharing button
pinterest sharing button
whatsapp sharing button
kakao sharing button
snapchat sharing button
sharethis sharing button
1
Quantity:

Foundation treatment engineering inspection

1. Introduction

Because of the large construction scale and dense underground pipe network, the ethylene glycol project of Binzhou Chemical Industry Company has high requirements for the stability and uniformity of foundation. The location of the project belongs to the collapsible loess layer prone to deformation under the action of water and pressure, causing the building to tilt or even collapse.

1

Site of treatment of collapsible loess foundation

2. Treatment solution

The ethylene glycol project of Binzhou Chemical Industry Company adopts the method of combining the measured value of field test with the calculated value of indoor test, which further improves the accuracy of collapsibility assessment. According to different grades of collapsibility and buildings, the foundation treatment methods such as dynamic compaction, compaction pile, deep dynamic compaction in hole and pile foundation were adopted to solve the problem of foundation collapsibility.

234

Comparison of soil samples before and after foundation treatment


3. Construction situation

The foundation treatment test and inspection for the ethylene glycol project of Binzhou Chemical Industry Company lasted for 16 months, with about 20000 geotechnical tests, about 3000 load tests, 120 standard penetration tests and some other in-situ tests.

567

Soil samples, laboratory tests and field tests


4. Achieved accomplishment

With different construction methods, the stability and uniformity of the foundation have been significantly improved. The results show that the dynamic assessment of loess collapsibility not only provides a reliable basis for optimal design, but also plays a guiding role in construction, which not only produces significant technical and economic benefits, but also ensures the engineering quality and prevents and reduces foundation collapsibility accidents. This method provides a technical idea for optimizing the treatment of large and collapsible loess foundation.

8

5. FAQ

Q1: Why not use pile foundation to directly penetrate collapsible loess layer to solve this problem?

A: Buildings or structures with different functions have different requirements for the engineering performance of foundations, so it is uneconomical to use pile foundations for foundation treatment, and the effect is not necessarily good.

Q2: What can you do in this field?

A: We can understand geotechnical engineering and geological engineering problems encountered in engineering construction.

Q3: What advantages do you have compared with other companies?

A: We serve design, construction and scientific research through geotechnical engineering survey, and have established an excellent technical team and a complete set of technical service systems.

Q4: What is the cost of geotechnical engineering test?

A: The cost will depend on many issues, such as geological conditions, test contents and test methods.


Hot Tags: foundation treatment engineering inspection, China, manufacturers, suppliers, factory, wholesale, price list, buy, for sale,

Previous: 
Next: 
CCTEG Xi'an Research Institute (Group) Co., Ltd. was founded in 1956, with the mission of leading the progress of coal technology and supporting safe and efficient mining.

QUICK LINKS

ABOUT US

Leave a Message
Get A Free Quote

CONTACT US

 Tel: +86-29-81778206 / 81778300
 After-sales Tel: +86-400-029-699
 E-mail: jingying@cctegxian.com
xiaoshou@cctegxian.com
 Add: No.82, Jinye 1st Road, High-tech Industrial Development Zone, Xi 'an, Shaanxi
 Copyright ©️ 2024 CCTEG Xi'an Research Institute (Group) Co., Ltd. All rights reserved. Sitemap I Privacy Policy